Project Details
Work Type: ITS
Phase: Completed
Length: 15.000 miles
City:
County:
Construction Cost: $1.05 Million
Project Start: Early 2019
Est. Completion: Early 2020
About

This project consists of installing dynamic message signs (DMS) along Interstate 75 (I-75) in Marion County as part of a statewide intelligent transportation system (ITS) initiative. Minimal traffic impacts are anticipated for the duration of the nearly one-year long, $1 million project.

There are two sign locations in the Ocala area. They are prior to the exits for State Road 326 (Exit 358) and County Road 318 (Exit 368) in both north and southbound directions.

Contact Information
Contractor
Florida Safety Contractors, Inc.